Timeline
As of 18 Oct 2026.
- Completed
- Working on
- Expected
- Milestone
- Buffer before deadline
- Overdue
Task / Sub task
Status
Sep 2026Oct 2026Nov 2026Dec 2026Jan 2027Feb 2027Mar 2027Apr 2027May 2027Jun 2027Jul 2027Aug 2027Sep 2027Oct 2027
285121926291623307142128411182518152218152229512192631017243171421285121926291623306132027
50% done
NB01: PointNet and PointNet++ baselines
Done
NB02: sampling retention gate
Done
NB02: sampling retention gate
Done · 15 Oct 2026 to 16 Oct 2026
Gate result: NO-GO on ForestSemantic-MS. Next: sparser UAV data.
Rerun the retention gate on sparser UAV data (FOR-instance)
Planned
Rerun the retention gate on sparser UAV data (FOR-instance)
Planned · 19 Oct 2026 to 30 Oct 2026
Class-weighted loss as a rebalancing control
Planned
0% done
◆
Write the review protocol (PRISMA 2020)
Planned
0% done
◆
E1 sampler against random, voxel, FPS, default and height-stratified
Planned
E1 sampler against random, voxel, FPS, default and height-stratified
Planned · 2 Nov 2026 to 27 Nov 2026
E1 go / no-go against height-stratified selection
Planned
E1 go / no-go against height-stratified selection
Planned · 30 Nov 2026
Fallback if no-go: CVPR 2027 EarthVision workshop or WACV 2028.
Register the ICCV abstract (est.)
Planned
Submit the ICCV paper (est.)
Planned
◆
◆
◆
0% done
Build and launch the MSc website
Working on
Build and launch the MSc website
Working on · 16 Oct 2026 to 31 Oct 2026
Migrate Notion tasks and seed papers, code and datasets
Planned
Migrate Notion tasks and seed papers, code and datasets
Planned · 26 Oct 2026 to 6 Nov 2026
Overdue (0)
None.
This week (0)
None.
Next 4 weeks (5)
- 24 Oct 2026 · Write the review protocol (PRISMA 2020) · P0 · Q1 review · Planned
- 30 Oct 2026 · Rerun the retention gate on sparser UAV data (FOR-instance) · First paper · height sampling · Planned
- 31 Oct 2026 · Build and launch the MSc website · Website · Working on
- 6 Nov 2026 · Migrate Notion tasks and seed papers, code and datasets · Website · Planned
- 13 Nov 2026 · Class-weighted loss as a rebalancing control · First paper · height sampling · Planned
Later (4)
- 27 Nov 2026 · E1 sampler against random, voxel, FPS, default and height-stratified · P1 · ICCV 2027 · Planned
- 30 Nov 2026 · E1 go / no-go against height-stratified selection · P1 · ICCV 2027 · Planned
- 1 Mar 2027 · Register the ICCV abstract (est.) · P1 · ICCV 2027 · Planned
- 8 Mar 2027 · Submit the ICCV paper (est.) · P1 · ICCV 2027 · Planned